From: Piers Cowley (formermarketgarden@gmail.com)

Dear Residents,

Next week we will finally start to felt and batten the roofs of plots 1 to 6.

The electricians and plumbers will continue to do the first fix to plots 1 to 6

A crane will be on site to lift up the first floor wall panels to plots 14,15 and 16.

the bricklayer should finish the sub structure blockwork to plot 10 with block and beam delivered on thursday.

The groundworker will commence dig and concrete to plot 11

Southern water will do our temporary water connection on the 16th

Regards

Piers

Former Market Garden Site  – w/c 15/5/23