Dear Residents,

Works are progressing well on site.

The timber frame to plots 14,15 and 16 is complete with plumbing and electrical 1st fix well underway. The facia and soffit is ongoing and looking to start the felt and batten next week.

The dry lining has commenced in plots 6,5 and 4. and the roofing nearing completion.

Plot 11 substructure is ongoing however the retaining wall is a slow process as we can only cavity fill a small amount at a time otherwise we risk the wall ‘blowing’. Once the sub structure is complete we will block and beam with a view to starting the timber frames to 9,10 and 11 in  July.

Regards

Piers