From: Piers Cowley (formermarketgarden@gmail.com)

Dear Residents,

We will be back on site on Tuesday due to the bank holiday.

On Tuesday there will be a crane on site to lift the trusses into position on plots 14,15 and 16.

The groundworkers will continue digging the foundation to plot 11, fixing the rebar Wednesday and pouring concrete Thursday.

The roofers will continue on plots 1 to 6.

The electrician and plumber will finish 1st fix to plots 1 to 6 and then it will be insulation and carpentry 1st fix and plasterboard.

The brickie will continue external brickwork to plots 1 to 6 following on after the roofers.

Regards

Piers

Former Market Garden Site w/c 30/05/23