Thankfully the better weather has arrived at last.

Plots 1 to 6 have had their first coat of paint internally. The brick/blockwork is 90% complete with the vertical tile hanging due to start shortly.

Plots 14, 15 and 16 have all been 1st fixed and the plaster boarding nearing completion.

Plots 9,10 and 11 timber frames are progressing well with a view to getting the trusses in w/c 18th september once the scaffold has been completed.

Plots 12 and 13 are now out of the ground with block and beam complete except for the garage on 13 which we are leaving down temporarily for access to the back of the plots.

Regards

Piers Cowley (formermarketgarden@gmail.com)