Dear Residents,
Another short week next week.
The trusses are complete on plots 1 to 6 with the facia ond soffits ongoing. The roofer will start felt and batten plot 6 on tuesday working towards plot 1.
We will also be starting m and e first fix next week in 1 to 6.
The sub structure blockwork is on going on plot 10 and the block and beam ongoing on plot 9.
The scaffold is ongoing on plots 14,15 and 16 with a crane booked for thursday to lift the first floor panels.
Open reach will commence the upgrade from site to Waites Lane as previously advised.
ThanksPiers
Market Garden Site w/c 08/05/23